Open During Road Construction

You can still access Ambassador Travel during the road construction on Oregon St. 
 
 
Construction work for City Contract 18-05 is continuing. The general contractor is PTS Contractors, Inc. out of Green Bay, Wisconsin. Please be advised that the schedule below is tentative and subject to change due to weather conditions. The final completion date for this project is October 26. City garbage/recycling will remain on your normal day. Please have your carts to the curb by 7:00 am. New street lights will be installed along Oregon St. between W 8th Ave and W 16th Ave. Please contact Dan Kussman, City Electrician at (920) 232-5350 for specific information. The No. 6 Bus Route that travels east along W 9th Ave crossing Oregon St and the No. 8 Bus Route that travels south along Oregon St through the entire project have been detoured Please contact GO Transit at (920) 232-5340 for specific information. The mail drop box located at the northwest corner of Oregon St and W 10th Ave has been relocated. Please contact thePostmaster at (920) 232-5760 for specific information.
 
To the best of our knowledge, AT&T has restored service to their customers after a major communication line was damaged on Thursday, April 5. For more information regarding your AT&T service, contact AT&T Customer Service. Thank you.
 
STREET INFORMATION
 
Oregon Street (Oregon St Bridge to W 8th Ave)
Work started on Friday, March 23 and is specified to be completed in five (5) weeks.
 
Oregon Street (W 8th Ave to W South Park Ave)
Work started on Friday, March 23 and is specified to be competed in sixteen (16) weeks.
 
Oregon Street (W South Park Ave to W 16th Ave)
Work is anticipated to start on or about June 4 and is specified to be completed in fourteen (14) weeks.
 
CONSTRUCTION ACTIVITY
 
Oregon Street (Oregon St Bridge to W 8th Ave)
PTS Contractors, Inc. has completed utility work in this section of Oregon St. Al Dix and MCC, Inc., subcontractors for PTS, will be starting sidewalk and asphalt pavement restoration work between the Oregon St Bridge and W 6th Ave on or about Wednesday, April 25.
 
Oregon Street (W 8th Ave to W South Park Ave)
PTS Contractors, Inc. will have two crews working. One crew will continue with sanitary sewer installation work between W 11th Ave and W 12th Ave. The other crew will continue with miscellaneous storm, sanitary and water main work south of W 8th Ave.
 
Oregon Street (W 8th Ave to W South Park Ave)
Falcon Drilling and Blasting Inc., a sub-contractor for PTS, will continue pre-drilling work for rock removal south of W 14th Ave.
 
 
PRIVATE UTILITY CONSTRUCTION ACTIVITY
 
Oregon Street (Oregon St Bridge to W 16th Ave)
AT&T will be making numerous adjustments to their facilities along the project route. Dig America, a subcontractor for AT&T, will continue telephone installation and facility infrastructure work between W 6th Ave and W 8th Ave. H&H utility, a subcontractor for AT&T, will be doing facility infrastructure work at W 8th Ave. Wisconsin Public Service (electrical) will be relocating and/or replacing utility poles along the project route. KS energies, a sub-contractor for WPS (gas), will have two crews working. One crew will continue with new gas main installation work south of W 14th Ave. The other crew will continue with new gas main installation south of W South Park Ave. Please note that all private utility construction work will be on-going and concurrent with the Oregon St reconstruction project.
 
TRAFFIC RESTRICTIONS
 
Oregon Street (Oregon St Bridge to W 6th Ave)
This section of Oregon St will remain open to traffic at all times with lane restrictions and flagging operations. The intersection at W 6th Ave will remain open at all times with lane restrictions. Traffic signals are currently turned off. Temporary stop signs are provided. Please anticipate these lane restrictions and be cautious when traveling this section of Oregon St and when traveling on W 6th Ave through the Oregon St intersection.
 
Oregon Street (W 6th Ave to W 11th Ave)
This section of Oregon St will be closed, local traffic only for business access. There will be limited on-street parking available. Pedestrian access to businesses will be provided at all times. The intersections at W 7th Ave and W 8th Ave  will be closed for private utility construction work. The intersection at W 9th Ave will be open with lane and turning restrictions. Traffic signals were removed. Temporary stop signs are provided. There will be construction equipment entering and leaving on W 9th Ave. Please anticipate these lane and turning restrictions and be cautious when traveling on W 9th Ave through the Oregon St intersection. Oregon St at W 11th will be closed. The intersection at W 11th Ave will be closed.
 
Oregon Street (W 11th Ave to W 12th Ave)
This section of Oregon St will be closed. Pedestrian access to businesses will be provided at all times.
 
Oregon Street (W 12th Ave to W South Park Ave)
This section on Oregon St will be closed, local traffic only There will be intermittent lane restrictions and construction equipment entering and leaving this section of Oregon St as the construction work continues south toward W South Park Ave. There will be limited on-street parking available. Pedestrian access to businesses will be provided at all times. Please anticipate these lane restrictions and be cautious when traveling this section of Oregon St. The intersection at W 12th Ave will be open with intermittent closures for construction work. At this time, the intersection at W South Park Ave will remain open. Traffic signals will be in operation There will be construction equipment entering and leaving on W South Park Ave. Please anticipate this and be cautious when traveling on South Park Ave through the Oregon St intersection.
 
Oregon Street (W South Park Ave to W 16th Ave)
This section of Oregon St is open to traffic. There will be intermittent lane restrictions and construction activity from private utility construction work and Contract 18-05 work. There will be limited on-street parking available. Pedestrian access to businesses will be provided at all times.  Please anticipate these lane restrictions and be cautious when traveling this section of Oregon St. Also, please anticipate the on-going construction activity and traffic restrictions on Oregon St between W South Park Ave and the Bridge.
 
W 6th Ave (Approximately 100’ east and west of Oregon St)
This section of W 6th Ave is open with lane restrictions and flagging operations. Please anticipate these lane restrictions and be cautious when traveling this section of W 6th Ave.
 
If you have any questions regarding the construction feel free to call the City of Oshkosh Engineering Division at (920) 236-5065 or talk to our Inspector who will be on site. Thank you and have a nice week.